Thursday, July 12, 2012

CVHE, CVHF, CVHG Water-Cooled CenTraVac Chillers


Installation, Operation, and Maintenance Guide
CVHE, CVHF, CVHG Water-Cooled CenTraVac™ Chillers
With Tracer AdaptiView™ Control

The unit nameplate is located on the left side of the control panel. A typical unit nameplate is illustrated below and contains the following information.
• Unit model and size descriptor
• Unit electrical requirements
• Correct operating charge and refrigerant type
• Unit test pressures and maximum operating pressures
• Unit literature
Serial Number - The unit serial number provides the specific chiller identity. Always provide this serial number when calling for service or during parts identification.
Service Model Number - The service model represents the unit as built for service purposes. It identifies the selections of variable unit features required when ordering replacements parts or requesting service.
Note: Unit-mounted starters are identified by a separate number found on the starter.
Product Description Block - The CenTraVac models are defined and built using the Product Definition and Selection (PDS) system. This system describes the product offerings using a product coding block which is made up of feature categories and codes that identifies all characteristics of a unit.

Table of Contents
Copyright
Trademarks
Warnings and Cautions
Model Number Description
Pre-Installation
ASHRAE Standard 15 Compliance
Unit Shipment
Installation requirements and Contractor responsibilities
Storage Requirements for chillers not yet installed
Unit Components
Unit Dimensions and Weights
Recommended Unit Clearances
Installation Mechanical
Operating Environment
Foundation Requirements
Rigging
Unit Isolation
Isolation Pads
Spring Isolators
Unit Leveling
Installation Water Piping
Overview
Water Treatment
Pressure Gauges
Valves
Strainers
Flow-Sensing Devices
Evaporator and Condenser Water Piping
Water Box Locations
Water Piping Connections
Grooved Pipe Coupling
Flange-Connection Adapters
Victaulic Gasket Installation
Bolt-Tightening Sequence for Water Piping Connections
Pressure Testing Waterside Piping
Purge Piping
EarthWise Purge Requirements - Purge Installation
Vent Piping
Refrigerant Vent-Line
Vent-line Installation
Insulation
Unit Insulation Requirements
Insulation Thickness Requirements
Installation Controls
Specifications
Installing the AdaptiView display
Adjusting the AdaptiView display arm
Electrical information
Installation Requirements
Electrical Requirements
Trane supplied starter wiring
Customer supplied remote starter wiring
Current transformer and Potential transformer wire sizing
Power Supply Wiring
Circuit Breakers and Fused Disconnects
Power Factor Correction Capacitors (optional)
Interconnecting Wiring
Starter to Motor Wiring (Remote-Mounted Starters Only)
Starter to control panel wiring
10kv-13.8kv Medium Voltage Installation
Motor Supply Wiring
System Control Circuit Wiring
Temperature Sensor Circuits
Unit Start-Up
Starter Module Configuration
Schematic Wiring Drawings
Operating Principles
General Requirements
Cooling Cycle
Oil and Refrigerant Pump
Motor Cooling System
AdaptiView Display
Tracer TU Chiller Service Tool
Start-up and Shut Down
Sequence Of Operation
Ice Machine Control
Free Cooling Cycle
Hot Gas Bypass
Hot Water control
Heat Recovery Cycle
Auxiliary Condensers
Control Panel Devices and Unit Mounted Devices
Unit Start-Up and Shut-down Procedures
Maintenance
Compressor Oil Change
Oil Change Procedure
Oil Filter
General Lubrication
Cleaning the Evaporator
Purge System
Long Term Unit Storage
Refrigerant Charge
Waterbox Removal and Installation
Discussion
Procedure
Connection Devices Information
Forms
Please Download Here

Kindly Bookmark this Post using your favorite Bookmarking service:
Technorati Digg This Stumble Stumble Facebook Twitter
YOUR ADSENSE CODE GOES HERE